Plan, budget, and manage multiple sub-projects under a single pre-approved business case using Project Pools. A Project Pool is a business case that has been approved but does not progress directly to a project. Instead, it acts as a parent that distributes its planned, budgeted, and approved amounts to multiple child sub-projects.
The benefit of using a Project Pool is that sub-projects linked to it are treated as pre-approved, which can eliminate or reduce the need for a full Delegation of Authority (DoA) approval cycle.
Key Concepts
A Project Pool is a business case flagged as a pool — it stays in approved status and does not progress to a project stage.
Sub-projects (children) are initiated as business cases and linked to the Project Pool as their parent.
When a sub-project is submitted, Planned (P), Budgeted (B), and Approved (A) amounts are automatically distributed from the pool to the child.
If a sub-project is fully covered by the pool's pre-approved amount, the DoA workflow is skipped.
If a sub-project exceeds the pool's remaining approved amount, the shortfall goes through the normal DoA process based on the full planned amount.
Distributions are triggered on submission — not on approval — to prevent two sub-projects from claiming the same funds simultaneously.
If a sub-project is rejected, returned, or deleted, its distributions are reversed back to the pool.
Only users who have access to the pool (via auth groups or as a Collaborator) can link a sub-project to it.
A Project Pool cannot be linked as a child of any other initiative. Nested pools (a pool that is itself a child of another pool or any initiative) are not supported and could cause unpredictable outcomes.
Allowed Relationships
Relationship | Allowed? | Notes |
|---|---|---|
Business case → Pool (child of a pool) | allowed | Standard sub-project pattern. The business case must not itself be flagged as a pool. |
Pool → Pool (pool as child of another pool) | not allowed | Nested pools are not supported. A pool cannot be linked as a child of another pool. |
Pool → any other initiative (pool as child) | not allowed | A Project Pool cannot be a child of any initiative type. It must always be the parent in a pool relationship. |
Pool Types Suffix
Pool Type | Label in dropdown | What gets distributed to child |
|---|---|---|
Budget Pool (proposal stage) | {pool description} (budgeted) | Budgeted (B) amount only |
Project Pool / Business Case Pool | {pool description} (approved) | Planned (P), Budgeted (B), and Approved (A) amounts |
Only Budgeted and Approved Pools should be displayed in the dropdown. Closed pools must not be available for selection and should be excluded from the dropdown list.
Create a Project Pool
Create a Proposal Initiative with desired Investment amount (do not flag as Pool)
Include the Proposal on Portfolio request and complete it
Proposal should be transitioned to Business Case
Tick the Pool checkbox on the business case form to flag it as a pool.
Complete the initiative then submit for approval through the normal workflow.
Once the CAPEX controller approves the business case, it will move to approved status — project ID is not required at this stage.
Create a Sub-Project Linked to the Pool
Create a new Business Case for the sub-project.
Save the initiative as a draft first to generate an Initiative ID.
Click the Link icon in the initiative header and add a Child relationship.
In the pool selection dropdown, choose the Project Pool — it will appear with an (approved) suffix. Closed pools should not be visible on the dropdown.
Complete and submit the business case as normal.
Amount Distribution on Submission
On submission, the system automatically distributes Planned, Budgeted, and Approved amounts from the pool to the child based on the child's investment amount.
Both the pool (parent) and the sub-project (child) headers will show the updated distribution amounts after submission.
The Parent tab on the child initiative shows all distributions that have been applied.
Click on any budget or approval amount in the Financial Summary to see where it came from.
DoA Approval Workflow for Sub-Projects
If the sub-project's planned amount is fully covered by the pool's remaining approved amount → DoA workflow is skipped. The sub-project moves straight to Capex Approval Requested and triggers SAP project creation.
If the sub-project's planned amount exceeds the remaining approved amount → the full planned amount goes through the normal DoA process (not just the shortfall). For example: if a pool is approved for $10M and sub-project 1 draws $8M (leaving $2M), then sub-project 2 is initiated for $2.5M — the DoA for sub-project 2 is triggered on the full $2.5M, not the $500k delta.
Once a sub-project completes the Capex Approval and SAP processes, it transitions to project stage and is managed as a standard project from that point.
Confirm the approval sequence by clicking the Participants icon in the initiative header.
Reversals — Rejected, Returned, or Deleted Sub-Projects
If a sub-project is rejected, returned, or deleted, all distributions are automatically reversed back to the pool.
If the sub-project's planned cost is reduced after submission, a partial reversal is processed. The returned budget cannot be less than the approved amount, and the approved amount cannot go below actuals or forecast.
Supplementing a Project Pool
If a Child initiative requires more funding than the Pool's remaining approved amount can cover, the Pool itself can be supplemented to increase its approved amount.
The supplement is raised on the Parent Pool, not on the Child directly.
Once the Pool supplement is approved, the Child initiative can proceed through its own workflow drawing on the newly available funds.
The supplement follows the standard approval chain (Manager → Sponsor → DoA) based on the total Pool value, inclusive of all amounts already distributed to Children.
Initiatives must be saved first to generate a unique ID before they can be linked to a pool.
After making changes to an initiative, click Save to refresh the distribution amounts and approval sequence.
Linked initiatives are maintained via the Linkages icon located alongside the Attachments icon on the initiative header.